WELCOME Cardinal Green Association RESIDENTS!

Progress update: 8.25.25

Roof replacements are all complete! Extra materials and bathrooms, etc. will be removed from the site this week sometime.

Progress update: 8.21.25

Roof replacements are continuing strong! We’ve completed buildings 1-4 and are currently working on building 5. We expect to finish building 5 today as well as roof load materials onto buildings 6 and 7. We plan to tear off buildings 6 and 7 tomorrow and will finish those two final buildings by end of day Sat., weather permitting. That will wrap up the project! Extra materials and bathrooms, etc. will be removed from the site next week sometime.

Progress update: 8.20.25

Roof replacements are going strong! We’ve completed buildings 1 and 2 are currently working on buildings 3 and 4. We expect to finish building 3 today and hope to also finish building 4 today. We will then move onto buildings 5 and 6 tomorrow, weather permitting.

Progress update: 8.19.25

Roof replacements are underway! We’ve completed building 1 and are currently working on buildings 2 and 3. We expect to finish building 2 today and hope to be about 50% done with building 3. We will then move onto buildings 4 and 5.

Parking:

We’ve worked with the Waukesha Police to arrange that from August 18th to August 29th, if residents can’t get back into their parking spots, they will not ticket Cardinal Green vehicles parked overnight on the street. All other posted parking signs still apply and must be followed.

What to expect:

Printable version of this page : What to Expect | Cardinal Green Association

We expect each building to take approx. 1-2 days to complete. We will have 2 crews working onsite and each on different buildings. We believe we will wrap up with all roof replacements in 1 week, again weather permitting.

There will be disruptions and required accommodations to be made by residents. We appreciate your patience throughout the project and your understanding as we work through repairs.

As with any large construction project, some issues are anticipated. Please report them to us as soon as possible so we can address accordingly. Please see the material delivery and roof load schedule below:

Monday 8/18 - Deliver and boom/load buildings 1-2 
Tuesday 8/19 - Deliver and boom/load buildings 3-4 
Wednesday 8/20 - Deliver and boom/load buildings 5-6 
Thursday 8/21 - Deliver and boom/load building 7 

Below is a map of the work site:

Vehicles * VERY IMPORTANT *

Have your vehicles off the driveway and moved out and away from your garage and building by 7:00 AM on the day(s) listed above to prevent damage to vehicles.


Suggestions to Ensure a Problem Free Roof

  • Remove patio furniture, grill and property from decks/patios as well as fragile items from walls, as these may incur damage during work. Contractor is NOT liable for such damages.

  • Please remove pet waste from your yard before the project starts to avoid messes on the roof and sidewalks, etc. as a result.

  • While we are working on your home, please close your window coverings during the day. This will help avoid any accidental embarrassments as the workers go up and down ladders to access the roof.


Landscaping

If there are any special or delicate plant or shrubs, please notify us of them before the job starts and we will protect them as best as possible.


Clean Up

One of the most important aspects of a project is keeping the area clean during the job. Here is how we strive to do this every day...

  • Clean your site during the day and at the end of the day.

  • Clean your lawn and site with our magnetic “nail-finder” to reduce chance of any nails being left in your lawn.

  • Keep our tools and materials neatly organized and out of the way.


Conditions beyond our control

Please be aware that despite our best efforts the following may occur during improvement projects, and are not the responsibility of the contractor:

  • Existing structural problems: Such as loose or cracked plaster and drywall, sagging rafters, nail-pops, bowed walls, previously rotted or damaged materials, etc.

  • Scheduling difficulties: We do our best to stay on schedule, but mother nature and other emergencies can lead to delays. We will do our best to limit delays.


Satellite Dish notice

Homeowners who have satellite dishes will be without service during the re-roofing of your building. Stronghouse Solutions/Capital Construction will reset the dish to the best of their ability, however if you experience issues please notify your service provider to schedule a service call for recalibration.

If you DO NOT want your satellite dish re-installed once the roof replacement is completed, please contact Josie Flicek before the start of your building by emailing josief@poweredbystronghouse.com so it can be properly disposed of.

Also here is a printable version of the Satellite Dish Notice


Questions

Please do not hesitate to contact Stronghouse Solutions with any questions or concerns via the website form on this page, or by contacting your account manager, Josie Flicek, at 866.989.6641 or at jflicek@stronghousebrands.com. Please let me know your address, name, email and phone number when you contact us. Thank you!